Project

Installation of Structural Steelwork

Project Value

£2,500,000

Date

February 2021

Job

Suez

Overview

The Watermark solution was to design, manufacture, delivery and installation of structural steelwork, plant & equipment, platforms, access equipment, mechanical pipework, and associated steel supports.

Case Study

Download PDF

Capability

Design, Fabrication, Installation,

installation of structural steelwork

Watermark Engineering Solutions was engaged by its client SUEZ (formerly Monsal Ltd) as preferred contractor for design, manufacture, delivery and installation of structural steelwork, plant & equipment, platforms, access equipment, mechanical pipework, and associated steel supports.

Most of the waste handled at the Eco Park comes from Surrey households, with any remaining capacity treating waste collected from businesses.

Charlton Lane Eco Park solution offered the following benefits:

  • GPS site scanning proved invaluable in determining modelled
    pipe runs through a congested plant

  • 3D modelling based on the scanned data allowed for production of
    accurate manufacture

  • Eliminated the need for onsite fabrications

  • On time delivery to provide continuity for the site install teams

  • £500,000 contract extension to carry out design improvements and modifications to existing installation of structural steelwork