Hemswell Cliff Waste to Energy Plant

Project Value

£103,027

Date

24/07/2019

Job

121

Overview

The Watermark design solution was designed in less component parts and transport

Case Study

Download PDF

Capability

Design, Fabrication, Installation,

This waste to energy plant project was situated in a residential area with restricted working hours impacting the programme of works.

The following design advice was offered to reduce site presence. Full off-site fabrication of skid mounted units designed around road transport limitations resulting in less component parts and transport.

All pumps, pipe work, electrical connections, thermal insulation and cladding incorporated into the unit offsite in works.

Slab marked out from construction 3D Model drawing and all units lifted into position in one day. Original waste to energy plant installation program shortened by 12 weeks and removed requirements for civils engineering works.